Sunday, October 31, 2010

WEEK 14 & 15 - 10/17/10 - 10/30/10

The past couple weeks we have: continued framing, installed gravel base in parking area, poured portions of the curb&gutter and started mechanical and electrical roughs. The framing has been slowed by recent heavy rains. Our schedule for the next few weeks include: start roofing 11/2, start fire sprinkler, continue with MEP roughs, pour more site concrete, and begin insulation.
Lots of Rain


Parking Gravel Base and Gurb & Gutter


Storage Building Foundation
Grease Trap
Mechanical and Electrical Roughs


7-Day Weather Forecast

Sunday, October 17, 2010

WEEK 12 & 13 - 10/3/10 - 10/16/10

The past few weeks has been more framing. All the site utilities are complete. We will pour the pavilion and storage building foundations next week. The MEP subcontractors will begin 'rough-in'(i.e. install boxes, conduits, pipes, duct, etc. inside the walls) the last week of October. Roofing is scheduled to start the week of 11/1. The framing will finish the first week of November.



Storage Building Foundation
Pavilion Foundation
Storm Sewer Inlet
Project Materials
Brick Mock-up
7-Day Weather Forecast

Sunday, October 3, 2010

WEEK 11 - 9/26/10 - 10/2/10

This week we starting framing; which will continue for 4-5 weeks. We have finished the site utilities and dirt work. The rock base for the paving has been re-scheduled for next week.




Framing Material and Roof Trusses


7-Day Weather Forecase