Sunday, October 31, 2010
WEEK 14 & 15 - 10/17/10 - 10/30/10
Sunday, October 17, 2010
WEEK 12 & 13 - 10/3/10 - 10/16/10
The past few weeks has been more framing. All the site utilities are complete. We will pour the pavilion and storage building foundations next week. The MEP subcontractors will begin 'rough-in'(i.e. install boxes, conduits, pipes, duct, etc. inside the walls) the last week of October. Roofing is scheduled to start the week of 11/1. The framing will finish the first week of November.


Storage Building Foundation
Pavilion Foundation
Storm Sewer Inlet
Project Materials
Brick Mock-up
7-Day Weather Forecast 
Sunday, October 3, 2010
WEEK 11 - 9/26/10 - 10/2/10
Sunday, September 26, 2010
WEEK 8-10 - 9/5/10 - 9/25/10
Sunday, September 5, 2010
WEEK 7 - 8/29/10 - 9/4/10
This week we continued with the foundation work (pouring stem walls). We also made all the water taps, ran the water lines, and started the storm water utility. Next week we will pour the remaining stem walls. Once the stem walls are complete, we can begin preparing the slab for concrete. All the utilities should be finished end of next week. The paving rock base will be installed around the middle of September.
I will be out of the office from 9/10-9/19. There will be no updates until I return. Thanks.
Building Foundation Work