Concrete bases were formed and poured for the parking light poles. The interior has received the installation of accordion folding doors in the cultural hall and chapel areas of the building. The wood floors have been sealed and painted and the interior has been wiped down and cleaned. The installation of door hardware continues to progress throughout the building.
Work has progressed as landscapers trenched around the building for irrigation lines. The electricians have installed exterior lights in the entry archways. The wood floor in the cultural hall has been finished and the court lines have been painted. Carpet has arrived as well as curtains.
Trenching for irrigation lines has begun on site as part of the landscaping work. The monument sign has been completed. The finish carpenters have installed the millwork on the front of the rostrum. Chalk boards and message boards have been hung in the classrooms and corridors. Wood flooring has been placed and will be recieving a finish coat next week.
Mow strip forms were placed around the site in preparation for concrete. Landscape gradation took place over various areas of the site. Light fixtures continued to be installed within the building. The finish carpenters installed wood trim and cabinets and work was performed on the sound and data systems. Site Gradation
The application of stucco to the exterior walls has been completed. The A/C units have received covers over their supply lines. Wood trim, cabinets and desktops were installed throughout the building. The restrooms have received the installation of ceramic tile. Stucco