Monday, August 9, 2010

WEEK 3 - 8/1/10 - 8/7/10

We have completed approximately 90% of the site grading. The concrete footings will start this coming Wednesday, 9/11. Site utilities (sewer, fire, storm) will start next week and continue for 15-20 days. The site grading should be complete by end of next week.