Over the last two weeks we have continued the rough-in of electrical, plumbing, HVAC, and fire sprinkler lines. We expect to be finished with the fire sprinklers within the next ten days. We continue to brick the exterior but progress has slowed due to some poor weather conditions. The steeple was set and we have poured the island curbing of the parking areas.