Monday, March 28, 2011
WEEK 36 - 03/20/11 - 03/26/11
EFIS continues to progress on the exterior of the building. Additional concrete sidewalks have been formed and poured. The mechanical pad has received a CMU wall. The interior has received light fixtures, sisal wall covering, acoustical ceiling tiles, and plumbing fixtures.
Sidewalks

Monday, March 21, 2011
WEEK 35 - 03/13/11 - 03/19/11
The walls and ceilings received more drywall mud and tape throughout the building, as well as sanding and texturing. The installation of tile is underway in the restrooms. The exterior received more masonry work, along with preparations for the installation of EFIS. The electricians set the power transformer and the concrete mechanical pad was poured.
EFIS Preparations

EFIS Preparations

Monday, March 14, 2011
WEEK 34 - 03/06/11 - 03/12/11
The exterior continues to receive the forming and pouring of concrete pours. The interior has received more joint compound and drywall tape. The electricians continued to install the brackets for lights and wires in the mezzanine areas. The floors in the bathrooms have received the installation of a mud bed in preparation for ceramic tile placement.
Concrete Sidewalks

Monday, March 7, 2011
WEEK 33 - 02/27/11 - 03/05/11
Masonry work has continued to progress on the exterior of the building. The site has received the installation of more concrete sidewalks and the mechanical pads were formed and poured. The application of joint compound and drywall tape is complete in the offices, corridors and classrooms. The mezzanines received more electrical work. Painting is scheduled to begin next week.
Masonry

Masonry