Monday, March 28, 2011
WEEK 36 - 03/20/11 - 03/26/11
EFIS continues to progress on the exterior of the building. Additional concrete sidewalks have been formed and poured. The mechanical pad has received a CMU wall. The interior has received light fixtures, sisal wall covering, acoustical ceiling tiles, and plumbing fixtures.
Sidewalks