WEEK 8-10 - 9/5/10 - 9/25/10

The construction is progressing well. We have poured the building slab and have completed about 95% of all site work and utilities. The framing will start Monday 9/27. Next week we will also install the rock base for the paving. Building Slab





Utilities (Fire Line, Storm Water, Electric Service)

7-Day Weather Forecast

Sunday, September 5, 2010

WEEK 7 - 8/29/10 - 9/4/10

This week we continued with the foundation work (pouring stem walls). We also made all the water taps, ran the water lines, and started the storm water utility. Next week we will pour the remaining stem walls. Once the stem walls are complete, we can begin preparing the slab for concrete. All the utilities should be finished end of next week. The paving rock base will be installed around the middle of September.

I will be out of the office from 9/10-9/19. There will be no updates until I return. Thanks.

Building Foundation Work



Storm Water Utility Pipe
Water Line Taps