Tuesday, June 21, 2011

WEEK 47 & 48 - 06/05/11 - 06/18/11

The Spring Hill Meeting House project has been successfully turned over to the LDS Church. We appreciate the efforts of all the team members who helped make this such a success: Architect, LDS PM, Church Leaders, Subcontractors and the efforts of the LDS Church members. The project was completed on time. We are grateful to be a part of this project and look forward to the next one.

Exterior Views





































Tuesday, June 7, 2011

WEEK 46 - 05/29/11 - 06/04/11

The parking stalls were striped and painted this last week. The landscaping crews continued to plant trees and shrubs, install irrigation lines and equipment, and spread bark mulch in flower beds. The completion of punch list items progressed throughout the interior of the building.

Parking Lot Striping




Landscaping







Irrigation Lines







7-Day Weather Forecast


Tuesday, May 31, 2011

WEEK 45 - 05/22/11 - 05/28/11

The site has received the planting of shrubs and trees as landscaping and irrigation continued to progress. Asphalt paving has taken place and was completed on the driveway and parking areas. The touch-ups to interior finishes continued throughout the building.

Planting and Irrigation










Asphalt Paving







7-Day Weather Forecast

Monday, May 23, 2011

WEEK 44 - 05/15/11 - 05/21/11

The parking and driveway areas of the site received more sub-base materials. These materials were spread and compacted in preparation for final paving of the parking lot. Irrigation lines continued to be installed and final site gradation has progress at various areas of the site. Ballads were set in the dumpster enclosure. Restroom partitions were installed and signage was mounted throughout the building.

Sub-Base Materials and Compaction















Irrigation Lines





Ballards


Restroom Partitions


Cabinet Signage


7-Day Weather Forecast


Monday, May 16, 2011

WEEK 43 - 05/08/11 - 05/14/11

Landscaping continued on site as irrigation water lines were installed around the building. Light poles have been installed while grading and compaction was performed on the parking areas. Glass cases were installed near the offices and the glass guardrail was installed in the font.

Landscaping












Grading and Compaction





Glass Case Glass Railing





7-Day Weather Forecast