The Spring Hill Meeting House project has been successfully turned over to the LDS Church. We appreciate the efforts of all the team members who helped make this such a success: Architect, LDS PM, Church Leaders, Subcontractors and the efforts of the LDS Church members. The project was completed on time. We are grateful to be a part of this project and look forward to the next one.
Exterior Views
Tuesday, June 21, 2011
Tuesday, June 7, 2011
WEEK 46 - 05/29/11 - 06/04/11
The parking stalls were striped and painted this last week. The landscaping crews continued to plant trees and shrubs, install irrigation lines and equipment, and spread bark mulch in flower beds. The completion of punch list items progressed throughout the interior of the building.
Parking Lot Striping
Parking Lot Striping
Tuesday, May 31, 2011
WEEK 45 - 05/22/11 - 05/28/11
Monday, May 23, 2011
WEEK 44 - 05/15/11 - 05/21/11
The parking and driveway areas of the site received more sub-base materials. These materials were spread and compacted in preparation for final paving of the parking lot. Irrigation lines continued to be installed and final site gradation has progress at various areas of the site. Ballads were set in the dumpster enclosure. Restroom partitions were installed and signage was mounted throughout the building.
Sub-Base Materials and Compaction
Sub-Base Materials and Compaction
Monday, May 16, 2011
WEEK 43 - 05/08/11 - 05/14/11