Tuesday, June 21, 2011

WEEK 47 & 48 - 06/05/11 - 06/18/11

The Spring Hill Meeting House project has been successfully turned over to the LDS Church. We appreciate the efforts of all the team members who helped make this such a success: Architect, LDS PM, Church Leaders, Subcontractors and the efforts of the LDS Church members. The project was completed on time. We are grateful to be a part of this project and look forward to the next one.

Exterior Views





































Tuesday, June 7, 2011

WEEK 46 - 05/29/11 - 06/04/11

The parking stalls were striped and painted this last week. The landscaping crews continued to plant trees and shrubs, install irrigation lines and equipment, and spread bark mulch in flower beds. The completion of punch list items progressed throughout the interior of the building.

Parking Lot Striping




Landscaping







Irrigation Lines