The site has received the planting of shrubs and trees as landscaping and irrigation continued to progress. Asphalt paving has taken place and was completed on the driveway and parking areas. The touch-ups to interior finishes continued throughout the building.
Planting and Irrigation
Tuesday, May 31, 2011
Monday, May 23, 2011
WEEK 44 - 05/15/11 - 05/21/11
The parking and driveway areas of the site received more sub-base materials. These materials were spread and compacted in preparation for final paving of the parking lot. Irrigation lines continued to be installed and final site gradation has progress at various areas of the site. Ballads were set in the dumpster enclosure. Restroom partitions were installed and signage was mounted throughout the building.
Sub-Base Materials and Compaction
Sub-Base Materials and Compaction
Monday, May 16, 2011
WEEK 43 - 05/08/11 - 05/14/11
Monday, May 9, 2011
WEEK 42 - 05/01/11 - 05/07/11
Concrete bases were formed and poured for the parking light poles. The interior has received the installation of accordion folding doors in the cultural hall and chapel areas of the building. The wood floors have been sealed and painted and the interior has been wiped down and cleaned. The installation of door hardware continues to progress throughout the building.
Concrete Bases
Concrete Bases
Monday, May 2, 2011
WEEK 41 - 04/24/11 - 04/30/11
Work has progressed as landscapers trenched around the building for irrigation lines. The electricians have installed exterior lights in the entry archways. The wood floor in the cultural hall has been finished and the court lines have been painted. Carpet has arrived as well as curtains.
Landscaping
Exterior Light Fixtures
Landscaping
Exterior Light Fixtures