Tuesday, May 31, 2011

WEEK 45 - 05/22/11 - 05/28/11

The site has received the planting of shrubs and trees as landscaping and irrigation continued to progress. Asphalt paving has taken place and was completed on the driveway and parking areas. The touch-ups to interior finishes continued throughout the building.

Planting and Irrigation

Asphalt Paving

7-Day Weather Forecast

Monday, May 23, 2011

WEEK 44 - 05/15/11 - 05/21/11

The parking and driveway areas of the site received more sub-base materials. These materials were spread and compacted in preparation for final paving of the parking lot. Irrigation lines continued to be installed and final site gradation has progress at various areas of the site. Ballads were set in the dumpster enclosure. Restroom partitions were installed and signage was mounted throughout the building.

Sub-Base Materials and Compaction

Irrigation Lines


Restroom Partitions

Cabinet Signage

7-Day Weather Forecast

Monday, May 16, 2011

WEEK 43 - 05/08/11 - 05/14/11

Landscaping continued on site as irrigation water lines were installed around the building. Light poles have been installed while grading and compaction was performed on the parking areas. Glass cases were installed near the offices and the glass guardrail was installed in the font.


Grading and Compaction

Glass Case Glass Railing

7-Day Weather Forecast

Monday, May 9, 2011

WEEK 42 - 05/01/11 - 05/07/11

Concrete bases were formed and poured for the parking light poles. The interior has received the installation of accordion folding doors in the cultural hall and chapel areas of the building. The wood floors have been sealed and painted and the interior has been wiped down and cleaned. The installation of door hardware continues to progress throughout the building.

Concrete Bases

Accordion Folding Doors

Door Hardware

Wood Floor Finish

7-Day Weather Forecast

Monday, May 2, 2011

WEEK 41 - 04/24/11 - 04/30/11

Work has progressed as landscapers trenched around the building for irrigation lines. The electricians have installed exterior lights in the entry archways. The wood floor in the cultural hall has been finished and the court lines have been painted. Carpet has arrived as well as curtains.


Exterior Light Fixtures

Wood Floor

Carpet Rolls


7- Day Weather Forecast