Due to rain, no work took place during week 5. During week 6, we poured the foundation footings, and installed the site sanitary sewer. Next week we will start forming the foundation stem walls and begin site storm water and fire line utilities.
Footings
Monday, August 30, 2010
Monday, August 16, 2010
WEEK 4 - 8/8/10 - 8/14/10
This week we started the underground plumbing and the foundation footings. We have completed about 95% of the rough grading. Next week we hope (pending weather) to pour the footings and start forming foundation stem walls. The sewer and fire lines will also start next week.