Brick has begun on the south end of the building and the site has received more concrete work including curbs and sidewalks. The electricians have begun the rough-in of the ceiling while removing the temporary lights. Drywalling continues to progress as well as the tie-in of HVAC equipment.
Brick
Curbs and Sidewalks
Monday, January 31, 2011
Monday, January 24, 2011
WEEK 27 - 01/16/11 - 01/22/11
Monday, January 17, 2011
WEEK 26 - 01/09/11 - 01/15/11
We started installation of HVAC furnance units this past week. Sheetrock on the walls has started and joint compound materials arrived in preparation for the taping of sheetrock. The suspended ceiling has been completed, and the MEP roughs have started working on the ceilings.
Snowy Conditions
Insulation
Snowy Conditions
Insulation
Monday, January 10, 2011
WEEK 25 - 01/02/11 - 01/08/11
Monday, January 3, 2011
WEEK 23 & 24 - 12/19/10 - 01/01/11
Over the last two weeks we have continued the rough-in of electrical, plumbing, HVAC, and fire sprinkler lines. We expect to be finished with the fire sprinklers within the next ten days. We continue to brick the exterior but progress has slowed due to some poor weather conditions. The steeple was set and we have poured the island curbing of the parking areas.
Steeple Installation
Steeple Installation
Subscribe to:
Posts (Atom)