Sunday, October 31, 2010

WEEK 14 & 15 - 10/17/10 - 10/30/10

The past couple weeks we have: continued framing, installed gravel base in parking area, poured portions of the curb&gutter and started mechanical and electrical roughs. The framing has been slowed by recent heavy rains. Our schedule for the next few weeks include: start roofing 11/2, start fire sprinkler, continue with MEP roughs, pour more site concrete, and begin insulation.
Lots of Rain


Parking Gravel Base and Gurb & Gutter


Storage Building Foundation
Grease Trap
Mechanical and Electrical Roughs


7-Day Weather Forecast