Thursday, December 2, 2010

WEEK 19 - 21 - 11/21/10 - 12/11/10

Project is progressing well. Framing and roofing are complete. The plumbing rough is complete and the HVAC and electrical are more than half way done. Steel door frames are being installed. Drywall has begun, starting with the mezzanine areas. The exterior is well underway on receiving a Tyvek wrap. Storefront entryways are complete and brick masonry has just begun. All concrete curb has been poured, and we will start asphalt paving just prior to turnover. We are scheduled to start drywall in the classrooms next week.