Monday, December 20, 2010

WEEK 22 - 12/12/10 - 12/18/10

The weather has been extra cold this last week and has really slowed down progress. We hope to see better weather next week and are doing all we can to push through with what work can be done in these conditions. HVAC duct work, electrical rough-in, and fire suppression piping have been able to continue but with some delay.

Weather Conditions 7-Day Weather Forecast

Thursday, December 2, 2010

WEEK 19 - 21 - 11/21/10 - 12/11/10

Project is progressing well. Framing and roofing are complete. The plumbing rough is complete and the HVAC and electrical are more than half way done. Steel door frames are being installed. Drywall has begun, starting with the mezzanine areas. The exterior is well underway on receiving a Tyvek wrap. Storefront entryways are complete and brick masonry has just begun. All concrete curb has been poured, and we will start asphalt paving just prior to turnover. We are scheduled to start drywall in the classrooms next week.

Curbing
Brick Installation
Framing


Storefront Entry
Plumbing
Electrical
Steel Door Frames
Drywall

HVAC and Fire Suppression Lines


Site

7-Day Weather Forecast