Monday, May 23, 2011

WEEK 44 - 05/15/11 - 05/21/11

The parking and driveway areas of the site received more sub-base materials. These materials were spread and compacted in preparation for final paving of the parking lot. Irrigation lines continued to be installed and final site gradation has progress at various areas of the site. Ballads were set in the dumpster enclosure. Restroom partitions were installed and signage was mounted throughout the building.

Sub-Base Materials and Compaction















Irrigation Lines





Ballards


Restroom Partitions


Cabinet Signage