Monday, February 28, 2011

WEEK 32 - 02/20/11 - 02/26/11

The exterior of the building continues to receive more masonry work. The landscapers began digging trenches in preparation to install irrigation water lines. Doors have been installed on the storage shed. Drywall installation is now complete on the interior of the building and filters have been applied over the openings to the HVAC lines. Joint compound and drywall tape will be installed over the next few weeks.