WEEK 32 - 02/20/11 - 02/26/11

The exterior of the building continues to receive more masonry work. The landscapers began digging trenches in preparation to install irrigation water lines. Doors have been installed on the storage shed. Drywall installation is now complete on the interior of the building and filters have been applied over the openings to the HVAC lines. Joint compound and drywall tape will be installed over the next few weeks.

Masonry


Trenches
Filters


7-Day Weather Forecast

Monday, February 21, 2011

WEEK 31 - 02/13/11 - 02/19/11

The interior walls and ceilings received more sheetrock and neared completion. The exterior continued to receive masonry work and the electricians have pulled wire to the electrical panels. The gas lines have been connected and curbing continued to be installed on site.

Sheetrock

Masonry Work
Concrete Curbing

7-Day Weather Forecast

Monday, February 14, 2011

WEEK 30 - 02/06/11 - 02/12/11

The snowy conditions temporarily affected the progress of site work but trenches were dug and gas pipes were installed successfully. The fire sprinkler riser was completed and insulation was installed in ceiling areas and wall cavities. Plumbers continued to work in the mezzanines while crews installed more drywall on corridor and classroom walls.

Snowy Conditions


Gas Line Trench
Fire Riser
Plumbing and HVAC
Insulation
Drywall

7-Day Weather Forecast

Monday, February 7, 2011

WEEK 29 - 01/30/11 - 02/05/11

Drywall installation continues to progress on the ceilings and walls within the building. The electricians have installed can lights in the chapel area. Masonry work continues on the exterior while the site has received more curbing and sidewalk installation.

Curb and Sidewalk
Drywall


Can Lights
7-Day Weather Forecast