WEEK 5 & 6 - 8/15/10 - 8/28/10

Due to rain, no work took place during week 5. During week 6, we poured the foundation footings, and installed the site sanitary sewer. Next week we will start forming the foundation stem walls and begin site storm water and fire line utilities.
Footings




Week 5 - No Work (We had to re-work all footing trenches & steel because of rain.)