Monday, August 16, 2010

WEEK 4 - 8/8/10 - 8/14/10

This week we started the underground plumbing and the foundation footings. We have completed about 95% of the rough grading. Next week we hope (pending weather) to pour the footings and start forming foundation stem walls. The sewer and fire lines will also start next week.
Rain

Font Plumbing


Fire Line Riser

East Parking and Grading



7-Day Weather Forecast