Sunday, August 1, 2010

WEEK 2 - 7/25/10 - 7/31/10

We have finished the grade for the building pad. Next week we will begin working on site utilities (storm sewer, fire line, etc.). Both the concrete and plumbing contractors will begin work on the pad the week of August 9.

Grade Building Pad


Grade Detention Pond



Silt Fence


7-Day Weather Forecast