WEEK 34 - 03/06/11 - 03/12/11

The exterior continues to receive the forming and pouring of concrete pours. The interior has received more joint compound and drywall tape. The electricians continued to install the brackets for lights and wires in the mezzanine areas. The floors in the bathrooms have received the installation of a mud bed in preparation for ceramic tile placement.


Concrete Sidewalks


Light Fixture Brackets

Joint Compound and Drywall Tape
Mud Bed