WEEK 36 - 03/20/11 - 03/26/11

EFIS continues to progress on the exterior of the building. Additional concrete sidewalks have been formed and poured. The mechanical pad has received a CMU wall. The interior has received light fixtures, sisal wall covering, acoustical ceiling tiles, and plumbing fixtures. Sidewalks

Mechanical Pad Wall
Light Fixtures

Acoustical Ceiling Tiles


Plumbing Fixtures
Sisal